Whitchurch Canal Basin Project
Updated Status September 29th 2011
Soil Test Results
The soil tests results are summarised for us by Platt White as follows:
“The soil test results confirm the material samples from these positions is within the inert waste criteria limit for landfill and is therefore not contaminated. Although it can be assumed the soil samples from the boreholes are representative of the site in general, it should be noted there is a possibility of isolated pockets of contaminated material which may be identified during excavation. This material would have to be disposed of accordingly.
The site is generally overlaid with approx 2-3m of made ground with rubble, brick and concrete fragments. Below this is a clayey sand soil, which can be reused as fill material to suitable areas of the site.
The bearing capacity of the made ground is predictably poor however the capacity of the clayey sand is higher and it is on this material that any foundations will be constructed. It should be noted the loads from the proposed retaining walls are relatively small due the nature of construction of the base of the walls which are wide to resist overturning moments exerted by the retained material. The width of the base distributes the loads from the wall over a whole base area which has the effect of reducing the total load per m2 bearing onto the subsoil.”
Based on these results Dave Lamb of Platt White has produced drawings.
Estimates have been made of the costs for constructing the basin. (See Below)
Estimates have been made for the costs of more detailed work needed to make a planning application. (see Below)
Basin Construction Costs
The Items for Costings estimate include:
Excavation of soil to reduced level (3000m3),
Disposal of surplus material to landfill (2500m3
fill to make up levels, embankments etc (500m3)
Piling to perimeter of canal and basin in PU6 section piles
Puddle clay lining and other filling eg stone to towpath
Retaining walls
Provisional sum for fencing and landscaping (landscaping amount to be agreed as a planning condition)
Provisional sum for steps and pedestrian ramp (may not be required depends on design of embankment)
Provisional sum for removal of access off Smallbrook Rd
Provisional sum for services diversions
Provisional sum for alterations to existing car park and surfacing
Total £418000 + contingency and construction design fees allow £475000.
Each 1m3 retained on site will save approx. £20/m3 so for example an additional 2000 m3 retained on site may be achieved with the revised design could save £40,000. Other adjustments to costs would include the size of the car park.
Planning Application Estimating The Cost
This would require:
Further drawings and section showing relationship with neighbouring property.
Provisional landscaping plan
Design & Access Statement
Planning Statement
Site plan showing associated works, eg car park alterations
Phase 1 & 2 Site Investigation report.
Engineering Fees (Platt White) for this are estimated at £3610.
Fees are subject to vat, the construction may be exempt (or recoverable) because it is new construction work.
The multiplier for the planning fee is £170 per 0.1 hectare, or part thereof. So the fee could be as high as 8 x 170 =£1360 depending on the area designated as being covered by the application.. If the town council makes the application, it would be halved.
For Environmental assessments a preliminary budget of up to £2000 was made. So far we have only had an initial ecology survey done so we are allowing £1300 for further report costs.
So the outstanding costs to pay as of September 2011 are about £5000 plus the planning fee costs plus VAT.
This is calculated as follows:
Platt White engineering drawings etc £3,610
General contingency other studies etc. £1,300
Total still to Pay £4,910
20% VAT £920
Total With VAT £5,830
Cost of the Initial Ecology survey(inc VAT) (already paid) £525
Total Cost For Planning Application (excluding the planning fee) £6,355
The work for the planning application by Platt White would consist of the following.
Plans, elevations and sections of the proposed works which will be a development of the plans already prepared and further plans and sections sufficient for the planning officer to visualise all areas of the scheme including an indicative landscaping plan. Existing site plan and location plan, these are required under all planning applications.
A design and access statement which is required with all applications which explains the development proposals, design, access sustainability, scale, compliance with policy etc and will include discussion on other reports such as site investigation, ecology etc and summarising any issues from these reports and detailing action required.
Completion of planning application forms, serving notice on landowners as required under the application and submission to the LA.
Dealing with planning officer queries during the consultation process.
DRAFT Action Plan
(1) Consult the public at Boat Rally and Blackberry Fair
(2) Study design issues to be addresses based on all comments received.
(3) Request consultant to advise on the impact of design options that have emerged.
(4) Convene a design review meeting with stakeholders and interested parties to settle all design issues.
(5) Instruct Consultant to proceed with planning application based on an agreed design brief.

